Sprague Avenue Preservation Project

ABOUT THE PROJECT 

The Sprague Avenue Preservation Project will grind and overlay the existing asphalt, replace concrete curb ramps to meet current accessibility guidelines, and repair existing stormwater systems to protect drinking water. The roadway will be striped to add an edge line to the outside lanes and reduce the center turn lane to standard widths. No lanes will be eliminated as part of this project.  

PROJECT SCHEDULE

While the project was originally planned for 2025, the ongoing Local Union 302 operator’s strike is impacting construction project schedules throughout the region. Currently, we anticipate the project to begin in early spring 2026. Though, it is possible that some preliminary project items will occur in late fall 2025. An update will be provided once the project schedule is finalized.

ANTICIPATED IMPACTS

Once the project begins, anticipated in spring 2026, the initial phases will require single lane closures for stormwater and curb ramp work. Access to all businesses will be maintained. 

The pavement grinding and overlaying will occur in two phases at night to minimize impacts on businesses. Overnight paving will require a full closure of Sprague anticipated to last for three nights. Business access may be restricted overnight while paving is occurring and will be coordinated with you prior. Details will be provided with the final construction schedule.

CONTRACTOR

At the Sept. 2, 2025, City Council meeting, the Council voted unanimously (7-0) to award the contract to Inland Asphalt.