[ARCHIVED] Addendum 3 - RFQ Engineering Services - Barker Road Improvements

City of Spokane
Valley Barker Road Improvements
ADDENDUM NO. 3

All consultants are required to base their Statement of Qualifications submittal upon the information furnished in this addendum. The following corrections/modifications are hereby made a part of the Request for Qualifications.

Request for Qualifications for Barker Road Improvements

All pages, delete all references to the “October 20, 2025 by 3:00 PM” submission date and replace with “October 27, 2025 by 3:00 PM”

Page 2, under “Scope of Work”, delete the first sentence of the second paragraph.

Page 2, under “Schedule”, replace this section with the following:

“The City anticipates the following schedule for completion of the RFQ and services outlined:

RFQ publication date:  September 19, 2025
SOQ submission date:  October 27, 2025 by 3:00 PM
Evaluation of SOQs:  Week of October 27, 2025
Notification of Finalist(s):  Week of November 3, 2025
Finalist(s) Interviews: Week of November 17, 2025
City decision by: Week of November 24, 2025
Anticipated start date: December 1, 2025”

Page 4, the “Schedule Approach” evaluation criteria max score is changed to 15 points.

Page 4, the “DBE Participation Plan” evaluation criteria is deleted. 